M/S. SWADESHI COTTON MILLS CO., LTD., KANPUR RA.JESHW AR PRASHAD AND ORS. I (P. B. GAJENDRAGADKAR, A. K~ SARKAR and K. N. WANCHOO, JJ.) Ind11strial Disp11te-Compromise during pendency of appeal- Validity-Procedure--The U. P. Ind1tstl'ial Disputes Act, I947 (U. P. XXV II I of Ig47), ss. 6-c, z(t)-U. P. Industrial Disputes Rides, Ig57, r. 5(I)-Payment of Wages Act, Ig36 (Act 4 of I93fi), s. 23. While this appeal by special leave, relating to an industrial rlispute was pending in this Court a Director of the appellant employer and a representative of the respondents' employees made an application to the Court praying that an order might be passed in terms of a compromise since an agreement was alleged to have been entered into by the appellants and the respondents. Some of the respondents contested this compromise and the court sent issues to the Tribunal for finding whether the alleged compromise actually took place between the parties, and if so, was it valid.

The Tribunal returned findings to the effect that the compromise did actually take place and was valid. Those findings were contested in the appeal. Held, that a compromise agreement seeking to settle an industrial dispute which was still pending decision in this Court would not contravene the provisions of s. 23 of the Payment of Wages Act which contemplated rights not likely to be modified or reversed in any judicial proceedings. The procedure prescribed by s. 6-C of the U. P. Industrial Disputes Act and the provisions thereof did not affect the powers of this Court, or the competence of the parties, to amicably settle a dispute pending before it. The procedure for obtaining an order in terms of the compromise entered into between the parties pending the appeal in this Court is prescribed by its own rules and the provisions of s. 2(t) of the U. P. Industrial Disputes Act and rule 5(1) of the Rules made thereunder have no application to such case. CIVIL APPELLATE JURISDICTION:

Civil Appeal No. 53 of 1958. Appeal by special leave from the Decision dated February 28, 1957, of the Labour Appellate Tribunal, Bombay, in. Appeal No. III-160 of 1956. S. P. Varma, for the appellants. Nove,.,ber r4. M fs. Swadeshi SUPREME COURT R.EPORTS [1961] L. K. Jha, Janardan Sharma, R. 0. Prasad and Maqbool Ahmad Khan, for the respondents. Cotton Mills Co., 1960. November 14. The Judgment of the Court Ltd., Kanpur was delivered by Rajeshwa• GAJENDBAGADKAR, J.-This appeal by special P1ashad &- Othm leave arises from an industrial dispute between the G . d-dk 1 appellant Messrs. Swa.deshi Cotton Mills and the res- •J•n raga a• . l l' . pon ents, its emp oyees, an t e s ort pre 1mma.ry question which is raised for our decision is whether an order should not be passed in this appeal in terms of the compromise agreement alleged to have been reached between the appellant and the respondents.

It appears that on December 28, 1955, an industrial dispute between the parties was referred by the Government of Uttar Pradesh to the Industrial Tribunal, U. P., Allahabad, for adjudication under ss. 3, 4 and 8 of the U. P. Industrial Disputes Act, 1947 (U.P. Act XXVIII of 1947) and in pursuance of the provisions of cl. 11 of G. 0. No. U-464(LL)/XXXVl-B-257 (LL)/1954 issued on July 14, 1954. The dispute thus referred was whether the existing rates of wages of jobbers mentioned in the annexure employed in the weaving department of the appellant need any revision; if so, with what details and from what date ? The Tribunal tried this issue and came to the conclusion that no case for revision had been made out by the respondents. Against this decision of the Tribunal the respondents preferred an appeal before the Labour Appellate Tribunal.

Their appeal succeeded and the Appellate Tribunal directed that the award of the original Tribunal should be set a.side, and that the appellant " shall introduce from the date of reference a uniform rate of two annas in both the old and new sheds irrespective of the number of looms assigned to the line jobbers". It would be noticed that as a result of this decision the existing rates have been revised and the revision has been ordered to take effect retrospectively from the date of reference. It is against this decision of the Labour Appellate Tribunal that the appellant has preferred the present appeal by special leave. Pending this appeal in this Court the appellant puri96o ported to enter into a compromise with the respon· Ml d , . s. - wa es,,. ents an t e terms o t e compromise were re uce Cotton Mills co .. to writing, and in pursuance of the said compromise Ltd., Kanpur a.n application was ma.de to this Court on February 26, 1958, signed by Mr. Bagla, on behalf of the appel- Rajes/iwar la.nt in his capacity as a.

Director of the appellant, a.nd Prashad &- Others Mr. Maqbool Ahmad Khan, for the respondents, in his Gajelldiacadl<ar J. ca.pa.city as the General Secretary of the Suti Mill Ma.~door Sabha, Kanpur. This application set out the material terms of the compromise. One of the terms of the compromise is that the revised rate should take effect not from December 28, 1955, which is the date of reference but from July I, 1957. Certain other modifications have a.lso been made in the decision under appeal. Before the appeal could be placed on the Boa.rd for passing orders in terms of this compromise an application was ma.de on behalf of some of the respondents alleging that the Genera.I Secretary Mr. Khan had no authority or power to enter into any compromise as a representative of the respondents, and that the compromise alleged to have been entered into by him with the appellant was not acceptable to the respondents.

In support of this case the application referred to a resolution passed by the General Council of the Mazdoor Sabha. whereby it was declared that no office bearer could conclude an agreement with an employer a.bout an industrial dispute without the consent of the General Council, and reliance was also placed on the relevant provisions in the constitution of the Mazdoor Sabha. Thereafter the petition for compromise was placed before this Court for hearing on April 10, 1960, and the Court directed that the application for recording compromise as well as the appeal itself should both be placed together for hearing before the Court as soon as the parties file their respective statements of the case.

After the statements were filed the appeal and the petition were placed before this Court on Ma.y 5, 1960, and the Court by an interlocutory judgment 46 [1961] '960 sent two issues to the Tribunal with a direction that M ;s. swadeshi the Tribunal should hear the parties on those issues Collon Mills Co., and make its findings thereon. The two issues were: Ltd., Kanpu, (1) Has the compromise set up by the appellant taken . v. place between the parties ; (2) If yes, is the com prop Rha;des;w•0'1, mise valid? In pursuance of this order the Tribunal rns a ~ ""' h d th as recor e ev1 ence, ear parties a.n ma. e its Gajendracadkar ]. findings. It has found that the compromise in fa.ct has ta.ken place as alleged in the petition made before this Court in that behalf, and that the said compromise is valid.

In dealing with the first question of fa.ct the Tribunal has considered the evidence exhaustively in the light of the background of the dispute between the parties; it has found that negotiations went on between the parties for a fairly long time during which period the parties discussed the pros and cons of the compromise, that during these nego· tiations Mr. Khan was watchful of the interests of the respondents, that the compromise had been approved by the workmen concerned, that on the whole it is to their advantage and does not a.t a.II militate against the accepted principles of industrial adjudication, and what is more it has been acted upon and has not remained a mere pa.per transaction. It has explained that the opposition to the compromise proceeded substantially from the dispute between Mr. Khan, the Secretary, and Mr. Ba.jpai, the President, and the Tribunal felt no doubt that the compromise was the result of bona. fide attempt on the pa.rt of both the parties to settle the dispute amicably in order to create goodwill and co-operation amongst the emplo· yer and the employees.

On the question of law raised by the second issue the Tribunal has held that the compromise is perfectly valid. It has considered the relevant provisions of the constitution of this Sabha, the practice prevailing in regard to such compromises and to several agreements of compromise entered into consistently with the said practice. It was urged before the Tribunal 1 that the compromise is invalid under s. 6-B of the U.P. Industrial Disputes Act, 1947, a.s well a.s s. 2(vi) (c) of the Payment of Wages Act, 1936 (Act 4 of 1936). These contentions have been rejected by the Tribunal. In the result the findings recorded on both the issues f th M/s. Swadeshi a.rem ia.vour o e compromise. c 11 M'll c After these findings were received in this Court, the 0 u;~. ;a~pu/"' appeal a.nd the compromise petition have now come before us for fine.I disposal. The finding of fa.ct Rajeshwar recorded by the Tribunal on the first issue has not Prashad &- Others been and cannot be challenged befo~e us.

It must Ga ·end;;;--;;dkar J. therefore be taken to have been established that at the 1 relevant time Mr. Khan was the General Secretary of the respondents' Sabha, and a.s such was entitled to represent them and did represent them during the course of the present adjudication proceedings, and that the compromise reached between him and the appellant is the result of mutual discussions carried on for some time and its terms on the whole are beneficial to the respondents. The practice prevailing in this Sabha and a large number of precedents which a.re consistent with the said practice indicate clearly that the Secretary of the Union who represents the workmen in industrial disputes · has always been authorised and has exercised his authority to settle such disputes when it was thought reasonable and proper to do so.

As we have often indicated it is always desirable that industrial disputes should be amicably settled because such settlement conducos to happy industrial relationship and encourages eo-opera.tion between the parties. Tha.t is why when industrial disputes a.re brought before this Court under Art. 136 of the Constitution this Court generally appreciates attempts made to settle disputes amicably, and in proper cases encourages such settlements. Mr. Jha, for the respondents, however, contends that though amicable settlement of industrial disputes may otherwise be desirable, in Ia.w such settlement or compromise is illega.I. If we come to the conclusion that compromise of industrial disputes pending an appeal is prohibited by law, or is otherwise inconsistent with such provisions it may be necessary to hold that the present compromise is bad in law however much amicable settlement of industrial disputes may otherwise be desirable. 'fherefore the question which arises for our (1961] decision on the present compromise petition is :

Is the contention raised by Mr. Jha correct that the compro- M /s. Swadeshi Cotto" Mill< co. mise is invalid in law? Ltd., Kanpur ' The first point urged by Mr. Jha in support of this argument is that the present compromise is prohibited Raj.,hwar bys. 23 of the Payment of Wages Act. This Act has Prashad & Others been passed to regulate the payment of wages to cer- Gajend~:dkar J. tain c.Iasses of persons employed in industry, and there is no doubt that the wages as revised by the Labour Appellate Tribunal in the present case would constitute wages under s. 2 (vi) of this Act. Section 23 provides that any contract or agreement, whether made before or after the commencement of this Aot, whereby an employed person relinquishes any right conferred by this Act shall be null and void in so far as it purports to deprive him of such right.

The relevant provisions of this Act require the fixation of wage periods, provide for the t-ime of payment of wages, authorises certain deductions, and permits the imposition of fines only subject to the conditions specified in that behalf. Section 15 of the Act provides for the determination of claims arising out of deduction of wages or delay in payment of wages and penalty for malicious or vexatious claims. Section 16 prescribes for the making of an application in which such claims can be set up; and s. 18 provides for the powers for the authorities appointed under the Act. Mr. Jha contends that the revised wage structure directed by the Labour Appellate Tribunal entitles the respondents to claim the respective amounts there indicated as their wages, and the effect of the impugned compromise is that the respondents are relinquishing a part of their right in that behalf. Mr. Jha contends that in giving up their claim for the retrospective operation of the decision of the Labour Appellate Tribunal for a substantial part of the period the respondents are required to contra.ct themselves out of their legal rights conferred by the award and therefore referable to this Act, and that makes the compromise invalid.

This argument is misconceived because it fallaciously assumes that the decision under appeal has become final and that the rights accruing under the said decision would not be and cannot be affected i96o by any compromise. The most significant fa.ct to 5 d h' remember in this .connection is th.at. the decis~on ?11 Cotto: J1.~~1:s ~o., which the alleged rights are based is itself sub3ect to Ltd. Kanpur an appeal before this Court, and in that sense it is not a final decision at all; it is liable to be reversed Rajeshwar or modified, and that being so the rights claimable Prashad 6- Otkm under the said decision a.re also liable to be defeated G . ·-'-dk 1 I . 1 a;e ..... raga ar . or materially affecte . n sue a case t e m . ustria dispute would undoubtedly be pending before this Court, and it would be idle for Mr. Jha to contend that an attempt to settle such a. dispute and not to invite a. decision of this Court contravenes the provisions of s. 23 of this Act.

Just a.s an industrial dispute could have been settled between the parties either before .it was referred for adjudication to the Industrial Tribunal, or after it was referred and before the a.ward was pronounced by the Tribunal, so would it be open to the parties to settle the dispute so long a.s it was pending either before the Labour Appellate Tribunal or before this Court. The provisions of s. 23 of this Act postulate certain definite rights which a.re not likely or liable to be modified or reversed in any pending judicial proceedings, and since this factor is absent in cases where an appeal is pending before this Court it would not be reasonable to rely on the said provisions and contend that they in substance prevent or prohibit amicable settlement of disputes. The other argument urged against the validity of the compromise is based on the provisions of s. 6-C of the U. P. Industrial Disputes Act, 1947. This section corresponds substantially to s.

19 of the Industrial Disputes Act XIV of 1947. It provides, inter alia, that an award shall in the first instance remain in operation for the period of one year or such shorter period as may be specified therein, and gives the State Government power to extend the period of operation from time to time if it thinks fit. It also provides that the State Government, either on its own. motion or on the application of any party bound by the a.ward, shorten the period of its operation, if it is shown that there has been a. material change in the circumstances [1961] '960 on which the award was based. The argument is Ml -5-d h. that any modification in the award can only be made s . . wa es I cotton Mills co., Y a optrng t e procedure prescribed by s. 6-C. In Ltd., Kanpur our opinion there is no substance in this argument.

Section 6-C undoubtedly confers upon the State Rajeshwar Government certain powers to fix the duration of the Praska~ others operation of the award, but there can be no doubt Gajendragadkar J. that the section can have no bearing on the powers of this Court in dealing with an industrial dispute brought before it under Art. 136 of the Constitution. The award to which s. 6-C refers is an award which has become final in the sense that it is no longer subject to consideration by any Tribunal or Court. So long as an award is pending before a Tribunal or a Court the jurisdiction of the Tribunal or the Court to deal with it in accordance with law is not affected by s. 6-C, and the competence of the parties to settle their dispute pending before the Tribunal or the Court is also not affected or impaired by the said section, In other words, what we have said about the argument based on the provisions of s. 23 of the Payment of Wages Act applies with equal force to the present argument as well.

Then it is contended that the impugned compromise is a settlement within the meaning of s. 2(t) of the U. P. Act and as such it can;be executed only in the manner prescribed by the Act. Section 2(t) defines a settlement as one which is arrived at in the course of conciliation proceedings and as including a written agreement between the employer and the workmen arrived at otherwise than in the course of conciliation proceedings when such an agreement has been signed between the parties thereto in such manner as may be prescribed and a copy thereof has been sent to the State Government and the conciliation officer. Rule 5(1) of the U. P. Industrial Disputes Rules, 1957, prescribes the procedure for recording a settlement as defined by s. 2(t). It is true that this procedure has not been followed, but it is difficult to understand how s. 2(t) or the procedure prescribed by r.

5(1) can have any application to a . compromise agreement which has been entered into between the parties pending the a.ppea.l in this Court. The compromise in question is intended to be filed in this Court for the purpose of M/s. Swadeslii enabling the parties to request this Court to pass an Cotton Mills Co., order in terms of the said compromise. The procedure Ltd., Kanpur for obtaining such an order which has to be followed . v. is the procedure prescribed by the rules of this Court, P Rka;des;wa0•1h just as if a compromise was reached before the Triburas a_.,,. ers nal the procedure to be followed before it would becajendragadkar J. the procedure prescribed by its rules. Therefore we have no doubt that the compromise in question cannot attract the procedure prescribed by r. 5(1).

The result is that the finding recorded by the Tribunal that the compromise in question is valid is obviously right a.nd must be confirmed.· Since it is found that the compromise in fact has ta.ken place and is otherwise valid, we have no hesitation in directing that an order should be drawn in terms of the said compromise in the present appeal. Order accordinyly. THE STATE OF BOMBAY M/S. RATILAL V ADILAL AND BROS. (J. L. KAPUR, M. HIDAY.A.TULLAR and J. C. SHAH JJ.) Sales Tax-' Dealer'-Meaning of-Appeal by special leave- Whenavailable-Bombay Sales Tax Act, I953 (Bom. III of I95J), ss. 27(I), (b), (c), 3o(I), 34(I) and (z)-Constitution of India, Art. I36. One Nanalal Karsandas, who was a brick manufacturer, held a priority certificate for purchasing coal under the Colliery Control Order and purchased a certain quantity of coal from M/s. S. G. Rungta Colliery through the respondents who were commission agents.

The respondents applied to the Collector for determining whether they could be described as "dealers" under the Bombay Sales Tax Act, 1953. The Collector held that they were dealers but the Sales Tax Tribunal held otherwise. No step was taken thereafter for a reference to the High Noveniber r5.