⚖️ Legal Sandook Supreme Court judgments

Supreme Court of India

Delta Mechcons (India) Ltd. v. M/s Marubeni Corporation

[2007] 7 S.C.R. 2812007 INSC 657
Decided18-05-2007
BenchP.K. Balasubramanyan
SubjectArbitration
ResultHearing Adjourned
CNRESCR010010392007
Open the judgment (PDF)

Judgment

CIVIL ORIGINAL JURISDICTION : Arbitration Petition No. 11 of 2006. (Under Section 11 (6) of the Arbitration and Conciliation Act 1998) M.C. Dhingra, Dr. V.K. Agrawal, Sunil Goel and Aarti Topu for the Petitioners. Harish N. Salve, Sr. Adv., Manu Nair and Viplav Shanna (for Suresh A. Shroff & Co.) for the Respondent. The Order of the Court was delivered by ORDER I. The respondent took up the project of construction of a thennal power plant at Ramagundam in Karimnagar District of the State of Andhra Pradesh. It entered into four sub-contracts with the petitioner relating to that work. The general conditions of sub-contracts were to be part of the four separate contracts. The sub-contracts were tenninated on 25.7.2001 with effect from 7.8.2001.

It appears that there were subsequent discussions between the parties and on the basis of ascertainment of the sums due to the petitioner the same were paid by the respondent and the petitioner i.n return gave in writing that it had received full and final paym(int from the respondent fu . tenns of the settlement between the two and also a certificate that all payments against the said four sub-contracts have been made by the respondent to the petitioner and received by the petitioner and that no bills are pending with the respondent for settlement. After the matters. rested on this basis, the petitioner made a claim in respect of the four sub-contracts. The petitioner also named an arbitrator and called upon the respondent to name an arbitrator in tenns of the arbitration agreement. The respondent disputed ·the claims of the petitioner and pleaded that there was no subsisting claim for the petitioner based on any of the four sub-contracts.

Even then without prejudice to its · contentions the respondent also named an arbitrator. In terms of the arbitration agreement, the two nominated.arbitrators had together to name the Chainnan ofthe Arbitral Tribunal or the presiding arbitrator. The nominated arbitrators failed to do so. 2. Meanwhile the petitioner had ·also moved the concerned District Court under Section 9 of the Arbitration and Conciliation Act seeking what it called interim protection pending an arbitration. Four separate applications were filed. The applications were dismissed by the District Court. The petitioner filed appeals in the High Court of Gujarat. The High Court disposed of the appeals recording the following: DELTAMECHCONS(INDIA)L TD. v. MARUBENI CORPN. [BALASUBRAMANY AN,J.]

283 "After having argued at some length, learned counsel on both sides A agreed and submitted that the main dispute between the parties is the subject-matter of separate arbitration proceedings and at this stage it may not be necessary or advisable to invite observations of this Court as regards the legality and validity of any of the claims or liability of any of the parties to satisfy such claims. It was, therefore, jointly B submitted that all the appeals may be disposed as withdrawn with the observation that the parties may put forward their case before the arbitral tribunal, which may decide the dispute referred to it without being influenced by any observation made in the impugned judgment as also the fact that these appeals were not pressed for any orders on merits." 3. The relevant clauses relating to arbitration, as contained in the agreement between the parties are as under: "21.

SEITLEMENTOF DISPUTES If at any time any question, dispute, or difference arise between the Contractor and the Subcontractor in connection with or arising out of the Subcontract or the Subcontract Works, either party shall give to the other notice in writing specifying the nature of such question, dispute or difference and the point at issue, and the parties shall discuss the matter and shall endeavour to reach an amicable settlement. In case parties fail to reach an amicable solution within sixty (60) days after the date of the said notice, the matter shall be referred to an arbitration in accordance with Clause 22 hereof. 22. ARBITRATION 22.

1Any dispute which could not be resolved between the parties in accordance with clause 21 hereof shall be settled exclusively by arbitration conducted in accordance with the Rules of Con citation and Arbitration of the International Chamber of Commerce. Each arbitral tribunal shall.consist of three arbitrators. The Contractor and the subcontractor shall each appoint one arbitrator and the two arbitrators thus appointed shall jointly agree upon the third arbitrator to act as chairman. If such agreement cannot be reached within thirty (30) days from the date of appointment of the later member, the third arbitrator shall be appointed by the International Chamber of Commerce. The said Chainnan shall not be the same nationality of either party to the sub-contract. 22.

2The arbitration shall be conducted in India 22.

3The language to be used on all written documents provided in each arbitration shall be English. 22.

4The decision of the arbitral tribunal shall be considered final and binding upon both parties and shall not be subject to any appeal whatsoever. 22.

5The cost and expenses of arbitration shall be borne by the party based on the award of the arbitral tribunal. 22.

6Performance of the sub-contract work shall continue during the arbitration proceedings notwithstanding the existence of any dispute, controversy or question." 4. When the named arbitrators failed to nominate a presiding arbitrator, the petitioner approached the International Chamber of Commerce (for short ICC) with a request that the presiding arbitrator may be nominated by the ICC. There was some correspondence between the ICC and the parties and ultimately the ICC informed the petitioner that the ICC had decided not to appoint a Chairman of the arbitral tribunal pursuant to the rules of ICC as appointing authority. It was in that context that the petitioner approached this Court with this application under Section I I of the Arbitration and Conciliation Act. 5.

Learned counsel for the petitioner submitted that going by the arbitration agreement the petitioner and the respondent have nominated their p arbitrators but the nominee arbitrators had failed to appoint a presiding arbitrator in terms thereof and in that context, as per the agreement, the petitioner had approached the ICC for nominating a presiding arbitrator but the ICC had refused the request without assigning any reason. In that context it-was submitted that the jurisdiction of the Chief Justice of India· - being an international arbitration - under the Act was attracted and it was just and necessary to appoint a presiding arbitrator in terms of Section I I of the Act.

This argument is controverted by the respondent, in addition to pleading on the merits that there was no subsisting claim for the petitioner and that the· arbitration is barred by limitation, by contending that the petitioner had not complied with the procedure set down by the ICC before calling upon ICC to name the presiding arbitrator and in that context the jurisdiction of the DELTA MECHCONS (INDIA) LTD. l'. MARUBENI CORPN. [BALASUBRAMANY AN,J.] 285 Chief Justice of India under Section I I of the Act is not attracted. It was also A contended that there were four sub-contracts and a single application for the appointment of a presiding arbitrator in respect of the disputes relating to four different contracts was not maintainable.

It was for the petitioner to have agreed to follow the ICC Rules and to comply with those rules so as to get an arbitrator appointed by the ICC in terms of their Rules and the petitioner having failed to do so, the application filed by the petitioner had only to be B rejected. The arbitration agreement clearly provides that dispute5 between the parties are to be settled exclusively by an arbitration conducted in accordance with the Rules of Conciliation and Arbitration of the International Chamber · of Commerce. It is hence submitted that the petitioner not having adhered to the said Rules, ICC was not justified in refusing to act. 6. It is true that there is a clause that the arbitration is to be conducted in terms of the Conciliation and Arbitration Rules ofICC. But it also provides that the arbitral tribunal shall consist of three arbitrators.

The contractor and the sub-contractor had to each appoint one arbitrator and the two arbitrators thus appointed, should jointly agree upon the third arbitrator as Chairman. If D such agreement be not reached within the time provided, the third arbitrator shall be appointed by the ICC. The Chairman was not to be ~f the same nationality of either party to the sub-contract. The arbitration agreement has to be read as a whole to know its purport.

7It is open to the parties while entering into an arbitration agreement E to provide as to how the arbitral tribunal should be constituted. It is also open to them to provide for the rules to be followed. As I read the arbitration agreement, I find that the parties had reserved unto themselves the right to· nominate an arbitrator each stipulating that the two arbitrators so nominated, should agree upon the third arbitrator to act as the Chairman. Jn other words, F the parties by their agreement have left it to the two arbitrators to appoint a third arbitrator to act as the Chairman. They have also agreed that in case of failure of the two arbitrators to appoint the third arbitrator, the third arbitrator was to be appointed by ICC. The parties had also provided that the arbitration should be conducted in accordance with the Rules of Conciliation and Arbitration of the International Chamber of Commerce. ·

8It was the contention of learned senior counsel for the respondent that once the machinery contemplated by the parties failed, the petitioner could only go by way of the. Rules of Conciliation and Arbitration of the International Chamber of Commerce and the petitioner not having proceeded H DELTAMECHCONS(INDIA)LTD.v.MARUBENICORPN.[BALASUBRAMANYAN,J.] 287 appointment of the presiding arbitrators since four sub-contracts were involved. A Even assuming that the contention has merit, I reject it as being too technical.

10There was not much argument before me on the merits concerning non-subsistence of any further claim for the petitioner and the request being barred by limitation. The parties proceeded on the basis that those were questions for the arbitral tribunal to decide. This might have been so particularly B · in the context of the stand adopted by them in the High Court of Gujarat in the appeals arising from the orders of the District Court in the applications under Section 9 of the Act. These questions have to be decided by the arbitral tribunal, in the circumstances of this case.

11As per the arbitration agreement the Chairman of the arbitral tribunal C has to be of a nationality different from the nationality of the contracting parties. Learned counsel for the petitioner contended that since the arbitrator was being appointed by the Chief Justice of India or his nominee in terms of Section 11 of the Act, this restriction would not apply and I was free to appoint anyone as Chairman or the presiding arbitrator. I am not in a position D to agree. In the light of my reasoning above, it is obvious that this part of the agreement between the parties must also be given effect to. Therefore, · this is a case where I have to appoint a Chairman of the arbitral tribunal who is of a nationality different from the nationality of either of the parties. Suffice it to say that for the moment I hold that my jurisdiction to name a Chairman of the arbitral tribunal has rightly been invoked and that a Chairman of the E arbitral tribunal has to be appointed by me. _ 12.

To enable me to name the Chairman, I direct, the parties either to . submit an agreed name with the consent of that person or in case they are not able to agree, submit two names each with the consent of the nominees, for being considered for appointment as the Chairman of the arbitra1 tribunal. F The parties are, therefore, directed to file either a joint statement-or separate statements in writing indicating the names as directed above 9n or before the 10th of July, 2007 and the matter will be posted for further orders on 13th July, 2007. RP. May be listed on 13th July 2007 for further orders. G