Supreme Court of India
Secretary to the Government, Transport Deptt., Madras v. Munuswamy Mudaliar & Ors.
| Decided | 29-08-1988 |
|---|---|
| Bench | Sabyasachi Mukherji |
| Case type | Civil Appeal |
| Subject | Arbitration |
| Result | Appeal(s) allowed |
| CNR | ESCR010004061988 |
Judgment
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3251 of 1988. From the Judgment and Order dated 21. 9 .1984 of the Madras High Court in C.R.P. No. 3482 of 1984. A. V. Rangam for the Appellant. P. Krishna Rao and K.R. Nagaraja for the Respondents. The Judgment of the Court was delivered by SABYASACHI MUKHARJI, J. Leave granted and the appeal is disposed of by the following judgment. SECY., TYT. DEPTT. v. M. MUDALIAR IMUKHARJI, J.] This appeal -arises out of an order of the fiigh Court of Madras, ·A dated 21st September, 1984. The appellant is the Secretary to the Gover.nment, Transport.Dept!., Madras, and the respondent-No. 1 is the· managing partner of M/s. National Company, whieh was the successful tenderer of the work of construction of a bridge across the river Coovum at Koyambedu witliin the corporation limit of the City of Madras and accordingly the necessary contract was executed between th~ responde1H No. 2-the Superintending Engineer (Highways)
Wprld Bank Project Circle, Madras, and the said Company on 28th April, 1979. According to the conditions of the contract between the parties, the work should have been completed on or before 5th November, 1980. The said National Company, however, according to the appellant, did not even commence the work till 21.9.1981 and despite exten- ~ion of time until 31.10.1981 the said firm failed and neglected even to commence the job. Consequently, the contract in favour of the said firm was determined absolutely at their risk and cost, according to the appellant. The respondent herein, in his individual capacity as managing partner of the said Company filed a suit in the City Civil Court, Madras, being O.S. No. 3996/82 claiming damages alleged to have been caused as a result of the said determination of the said contract and for refund of earnest money deposit etc. In view of the Arbitration Clause under the agreement betweeri the parties, the appellant filed a petition for referring the dispute to the arbitrator for further proceedings and the City Civil Court, Madras, accepting the appellant's prayer, passed orders directing both the parties"to refer the. disputes to the arbitrator, and stayed the suit, As per the order of the City Civil Court, Madras, the respondent filed. claim petition before the arbitrator, namely, Superintending Engineer (Highways & Rural Works), Rural.Roads Circle, Tiruchirapalli, being the second respondent herein. · During the pendency of the ciaim before the said arbitrator, the . respondent filed another application seeking to change the arbitrator . on the· ground that ·the arbitrator· being an employee of the· State Government, an Engineer froin any ·sector other than t!H,. sector of Tamil N adu or a retired Engineer of the State Government might be appilintedas -arbitrator.
The contract between the parties, inter. alia, contairted the following Arbitration Clause: 0 SUPREME COURt.REPORTS [1988] Supp. 2 S.C.R. "(3) The.atgitrator for fulfilling the duties set forth in the arbitratioi'i clause of the Standard Preliminary Specification shall be Superintending Engineer (H) Rural. Roads Tiruchira Palli Ci_rcle." Pursuant to this the Superintending Engineer of that Circle, at the relevant time, was previously appointed as arbitrator. There was succession to that office by another incumbent and the succeeding Superintending Engineer. wanted to continue the arbitration proceedings but before that an application was made under Section 5 of the Arbitration Act, 1940 (hereinafter called 'the Act') for removal of the arbitrator, before the learned Judge of the City Civil Court, Madras. The learned Judge by his order sought to revoke the authority of the named arbitrator. The learned Judge in his order dated 6th March, 1984., inter a/ia, observed as follows:
"The apprehension of bias on the part of the Arbitrator is made to rest on the ground that the first respondent in the counter filed before the Arbitrator to the claim made by the petitioner referred to G.O. Ms. 409/Transport Dated 7.4.83 which in tum made a reference to a letter No .. 114879/D2/81. Dated 30.10.82 of the Chief Engineer, H & RW." In the order of the learned Judge, City Civil Court, he stated that the Chief Engin~er of the Circle concerned was in favour of the cancellation of the contract in question and the contract entrusted to the petitioner came to be terminated and the construction was sought to be entrusted at the' risk and cost of the petitioner on the advice or the JP proposal of the Chief Engineer.
The Superintending Engineer is subordinate to the Chief Engineer, therefore'· the learned Judge, City Civi!Court was of the view, as he says in the judgment, "It is not unreasonable to say that the successive Superintending Engineer of this particular department who will be subordinate to the Chief Engineer will necessarily have _a leaning to accept the attitude expres- (jJ sed by the Chief Engineer." The learn!>d Judge came to the cor1clusion tharthere could legitimately be a bias in the mind Of the arbitrator w!Jo was the Superintending Engineer against the appellant. The High Court also did not examine this _aspect and dismissed_ the appeal in 1 imine. H'ence, this appeal. !fl Apprehensiew-of bias in the ,rii,ind .of the arbitrator is a good SECY., TPT. DEPTI. v. M. MUDALlAR [MUKHARJI, J.] ground for reinovaf of~the ·arbitrator under section 5 of the Act.
The learned Judge, City Civil Court, had directed the parties to submit a · A list of three engineers willing to be appointed as arbitrator and if the parties ex1>ress consensus one of the three from the list of the petitioner or from the list of the respondent would. be chosen and appointed.as arbitrator and in case. there is no consensus between..the. parties then from among six.engineers to bt mentioned by both the parties three el!ch in a separate list one of them will be selected by draw of lots and ·appointed as arbitrator. The parties were directed to submit a list of three engineers of their choice who would be willing to be appointed as arbitrator"in the.matter within.a stipulated period. This is;li. case of removal ofa n'!ffied arl:iitrat9r under Section 5 of . the kct which gives jurisdi!'tion to the.Cciubto revoke the authorit)' of·· C the •arbitrator. ·when the parties entered into the contract., the parties knew the terms of the contract includihg arbitration ·~lause.
The parties knew the scheme and· the fact that ·tlie <:;hief Engineer is superior and .the Stipe5intending'Engfr1eer is subordinate to the Chief Engineer of the particular Circle. ln spite cif that the parties agreed and o .enterl'd irtto arbitration an_d indee,d submitted to the,jurisdiction of the Superintending Engineer at thai time·tobegin with, who, however, could. not· complete the arbitration be~ause' he was transferred and suc<;eeded by a successor. In. those circum~tance.s on the facts stated no bias can reasonably be ·apprehended and made a ground for removal of a named arbitrator. ln our opin;(on thi.s cannoJ_b_e, at all, a good or . E. valid legal ground. Unless there is allegation against the named arbitrator either against his honesty or capacity or ma/a fide or interest in the subject matter or reasonable apprehension of the bias, a named and agreed arbitrator cannot and should not be removed in exercise of a discretion vested in the Court under section 5 of the Act.
Reasonable apprehension of bias in the mind of a reasonable man can be a ground for removal of the arbitrator. A predisposition to decide for or against one party, without proper regard to the true merits of the dispute is bias. There must be reasonable apprehension of that predispositipn. The reasonable apprehension must be based on cogent material~. ~ee the observations of Mustill and Boyd, Commercial Arbitration, 1982 Edition, page 214. Halsbury's Laws of England, Fourth Edition, Volume 2, para 551, page 282 describe that the test for bias is whether a reasonable intelligent man, fully appraised of all the circumstances, would feel a serious apprehension of bias. This Court in International Authority of India v. K.D. Bali and 'UPREME COURT REPORTS I 1988] Supp. 2 S.C.R. Anr., J.T. 1988 2 S.C. l held that there must be reasonable evidence to satisfy that there was a real likelihood of bias.
Vague suspicions of whimsical, e<apricious and unreasonable people should not be made the standard to regulate normal human conduct. In this country in numerous contracts with the Government, clauses requiring the Superintending Engineer or some official of the Govt. to be the arbitrator are there. It cannot be said that the Superintending Engineer, as such, cannot be entrusted with the work of arbitration and that an apprehension, simpliciter in the mind of the contractor without any tangible ground, would be a justification for removal. No other ground for the alleged apprehension was indicated in the pleadings before the learned Judge or the decision of the learned Judge. There was, in our opinion, no ground for removal of the arbitrator. Mere imagination of a ground cannot be an excuse for apprehending bias in the mind of the chosen arbitrator.
In that view of the matter, the order made by the learned Judge, City Civil Court, and the decision of the High Court cannot be sustained and they are set aside. The appeal is allowed. We remand the case back to the learned Judge, City Civil Court, to ask the Government to appoint the Superintending Engineer, Trichy, to be an arbitrator in accordance with the arbitration agreement. The arbitrator will proceed according to the evidence of the parties and after considering all the relevant facts according to the agreement and make an award in accordance with law. There will be no order as to costs. P.S.S. Appeal allowed.